Canada's particle accelerator centre
Centre canadien d'accélération des particules

Target Summary Info

Target Name
Target Station
Target Module
HP/LP
Ion Source
Note
Start Date
End Date
Schedule Link
DocuShare
Ta#60 ITW TM2 LP SIS 138 Collection-29245


Details

Target Details
Installed Date Planned Start Date 2020-09-17
Heaters/ ECR On Weight [kg]
Target Material [g] Backing Material [g]
Removed Shipping Date
Proton Beam
Impedance [mΩ] BIAS [kV]
Rated p+ [μA] Peak p+ [μA]
Net Charge [μAh] Est p+ Charge
Assays
Assay 1 [μSv/h] @1m 83200 Assay 1 Date 2020-10-21
Assay 2 [μSv/h] @1m Assay 2 Date
Assay 3 [μSv/h] @1m Assay 3 Date
Assay 4 [μSv/h] @1m Assay 4 Date
Assay 5 [μSv/h] @1m Assay 5 Date
Dose rate OC F-308 μSv/h [mSv/h] Dose rate @1m F-308 μSv/h [mSv/h]
Date of Sent Days to Ship
Calculated Ship Days Optimistic
Schedule Start 2020-9-17 Schedule End 2020-10-6
Estimated Ship Days 511 Estimated Ship Years 1.39923287671233
Vault Location 7B Pail 239
Vault Comment
Target Assayed