Nb#8 ITW TM2 HP SIS 2018-7-11 2018-7-22 134 Collection-22548


Details

Target Details
Installed Date 2018-7-3 Planned Start Date 2018-07-11
Heaters/ ECR On 2018-7-5 Weight [kg]
Target Material [g] Backing Material [g]
Removed 2018-7-31 Shipping Date
Proton Beam
Impedance [mΩ] 12.9 BIAS [kV] 13
Rated p+ [μA] 100 Peak p+ [μA] 65
Net Charge [μAh] 5305.78 Est p+ Charge 1.184e+20
Assays
Assay 1 [μSv/h] @1m 71100 Assay 1 Date 2018-8-2
Assay 2 [μSv/h] @1m 2019-11-4 Assay 2 Date 2740
Assay 3 [μSv/h] @1m Assay 3 Date
Assay 4 [μSv/h] @1m Assay 4 Date
Assay 5 [μSv/h] @1m Assay 5 Date
Dose rate OC F-308 μSv/h [mSv/h] Dose rate @1m F-308 μSv/h [mSv/h]
Date of Sent Days to Ship
Calculated Ship Days 162 Optimistic 122
Schedule Start 2018-7-11 Schedule End 2018-8-1
Estimated Ship Days 1043 Estimated Ship Years 2.85830136986301
Vault Location 2A Pail 168
Vault Comment